Project Development

The development phase of a solar project takes up to two years and requires the navigation of numerous regulations and governmental agencies.
Geenex is here to guide landowners and other partners through this complicated process.

Land acquisition, site analysis, environmental assessments, facility permitting, utility interconnection and power purchase agreements are key parts of the due diligence process in solar development for which Geenex can offer our expertise. As Geenex is uniquely focused on the development of solar facilities, we are in an optimal position to provide the best leadership and oversight for such projects.  This collaborative development effort is what makes us your local greenfield developer.

Geenex’s proven processes and experienced team members are what has enabled us to quickly build an extensive development pipeline in only a few short years. With a primary focus on facilities between 20 MW and 100 MW in size, Geenex has a proven track record of success.  Our partners and investors understand that our projects will be developed on-time, on-budget, and in-accordance with all local, state and federal permitting requirements.

Sample Project Development Timeline

Month

1-6

  • Sign Contract with Landowner
  • File interconnection
  • Preliminary due diligence and site inspection

Month

7-13

  • Receive interconnection feasability report
  • Begin full site analysis
  • Begin County, State and Federal permitting processes
  • Begin negotiation with investor

Month

14-20

  • Receive interconnection feasability report
  • Complete permit
  • Attain all permits
  • Finalize negotiation with investor

Month

21-24

  • Sign inter- connection agreement
  • choose GC firm